close icon

Contact Us

close icon

Corporate Office
Address

29th & 30th Floors,
World Trade Center,
Brigade Gateway,
#26, Dr Rajkumar
Road, Malleshwaram,
Bengaluru, Karnataka
560055.

Dubai Branch Office

Brigade Enterprises Limited,
708, Atrium Centre,
Bank Street,
Bur Dubai,
Dubai.

Site Address

#5/142,
Rajiv Gandhi Salai,
Old Mahabalipuram Road,
Perungudi,
Chennai 600096.

Request
a callback

Please enter your name
Please enter your email
Please enter valid email address
Please enter your country code
Please enter your phone
Please enter valid contact number
Please click the checkbox

Request
a callback

Thank you for sharing your details with us. Our team will get in touch with you shortly.

Okay

Contact Us

close icon
Please enter your name
Please enter your email
Please enter valid email address
Please enter your country code
Please enter your phone
Please enter valid contact number
Please click the checkbox

One Time Password Verification

Verification number sent to your Mobile :
+91 7904501736

Please enter valid OTP

Didn’t receive the OTP?  RESEND

Verify OTP
sub menu

Project Status

image

Towers A1 and B1: Slab level completed - Status as of October 2020

image

Tower A1: GF slab in progress - Status as of October 2020

image

Towers A1 and B1 to GF column 50% completed - Status as of October 2020

image

Non-tower area: 35% raft completed - Status as of October 2020

image

Non-tower area: B1 slab 35% completed - Status as of October 2020

image

Tower A1—Raft completed; Tower B1—slab 60% completed - Status as of September 2020

image

Non-tower Area: 30% raft completed - Status as of September 2020

image

Tower A1—raft completed; Tower B1—slab formwork under progress - Status as of August 2020

image

Tower A1—Raft Completed; Tower B1—slab formwork under progress - Status as of August 2020

image

Non-tower area: Pour 1—raft completed and columns in progress; Pour 2—raft work-in-progress; A2 excavation completed. - Status as of August 2020

image

Tower A1 PCC 100% completed, raft waterproofing 100% completed, 75% raft concreting completed and balance in progress - Status as of July 2020

image

Tower A2 Excavation status - Status as of July 2020

image

Tower A3 and part podium excavation completed - Status as of July 2020

image

Excavation work-in-progress (60,000 Cum completed till now) - Status as of July 2020

image

Tower A1: PCC 100% completed, raft waterproofing 85% completed, reinforcement work-in-progress - Status as of June 2020

image

Tower A2: Excavation under progress - Status as of June 2020

image

Tower A3 and part podium excavation completed. Tower crane foundation completed - Status as of June 2020

image

Excavation work-in-progress (55,000 Cum completed till now) - Status as of June 2020

image

Tower A1: Excavation work completed - Status as of May 2020

image

Tower A1: PCC works under progress—40% completed - Status as of May 2020

image

Tower A1: Excavation work completed - Status as of May 2020

image

Towers A2 and A3: Excavation work nearing completion - Status as of May 2020

image

Excavation work completed for Tower Astra - Status as of March 2020

image

PCC work under progress for Tower Astra-30% completed - Status as of March 2020

image

Excavation work under progress for Tower Zenith & Tower A3 - Status as of March 2020

image

Excavation work in progress Clubhouse Tower(40,800 completed till now)- Status as of March 2020